Project Deliverables - Is it possible to get lead time from cum lead time?


akin
Do Gooder (Customer)
Forum|alt.badge.img+1
  • Do Gooder (Customer)
  • 3 replies

Dear IFS Community,

I have calculated the cumulative lead time for all the parts. When I generate a plan for a manufacturing part in the project deliverables module, it calculates according to manufacturing lead time. Is there a way to make it generate according to cum lead time instead?

 

For instance, 

 

Best answer by Dinidu Udana

Hi @akin ,

The standard application design is to take the manufacturing lead time only. I was hoping that you could look in to a modification to get the cum lead time as required. 

Hope this Helps.
Regards,
Dinudu Kankanamge.
IFS Unified Support

View original
Did this topic help you find an answer to your question?

3 replies

akin
Do Gooder (Customer)
Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • 3 replies
  • May 28, 2024

Any help?


Dinidu Udana
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • 71 replies
  • Answer
  • May 29, 2024

Hi @akin ,

The standard application design is to take the manufacturing lead time only. I was hoping that you could look in to a modification to get the cum lead time as required. 

Hope this Helps.
Regards,
Dinudu Kankanamge.
IFS Unified Support


akin
Do Gooder (Customer)
Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • 3 replies
  • May 29, 2024

Dear @Dinidu Udana 

 

Thank you for the reply.

 

Regards,

 

AKIN