Hi,

 

For our projects, we need sometimes to transfer 50+ parts to project inventory. Is the only option to do this line by line with material transfer requisition? We would like to have a one click solution.

1 reply

wrprabash
Hero (Partner)
Forum|alt.badge.img+10
  • Hero (Partner)
  • 72 replies
  • November 21, 2022
First Employee wrote:

Hi,

 

For our projects, we need sometimes to transfer 50+ parts to project inventory. Is the only option to do this line by line with material transfer requisition? We would like to have a one click solution.

Hi,

Have you tried 'Inventory part in stock’ client ?. With that you can select as many as stock and then by action 'transfer to project inventory’, moves the stock to specified project inventory.

Regards,

Roshan