Skip to main content
Question

Unable to multi-edit | "Activities" screen

  • August 9, 2022
  • 1 reply
  • 68 views

Ushan Senarath
Hero (Employee)
Forum|alt.badge.img+10

Hi,

 

The Edit all functionality is not available for the ‘Early start’ and ‘Early Finish’ tabs in the ‘Activities’ screen in the cloud.

 

 

However, this functionality is available in the ‘Project Transactions’ screen

 

Yes, it’s understood that IEE client and cloud are not matched one to one.

But for your reference, the replace all functionality is available in IEE in “Activities’ Screen allowing the users to do a mass edit.

 

A customer has reported that “major use of find and replace by PMs right now is to update the start and finish dates of activities in bulk via the ‘Activities’ window”.

Hence look into implementing specific actions/commands to enable users to do a multi-edit in the ‘Activities’ screen considering the business scenario mentioned above.

 

Best regards,

Ushan

1 reply

Ushan Senarath
Hero (Employee)
Forum|alt.badge.img+10
  • Author
  • Hero (Employee)
  • 45 replies
  • August 9, 2022

This has been routed for the Idea wall


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings