FSM Resource Scheduling concepts


Sashika Lakshan
Hero (Employee)
Forum|alt.badge.img+7

Hi,

Can someone please clarify when considering scheduling concentrations in FSM, What are bellow concepts referring to.  

  • Duration of activity
  • Regions
  • Availability

This information will be useful to investigate an error reported on resource allocation.

Thanks 

Best answer by Tharindu Rasnakawewa

Hi Sashika,

Mainly there are more concepts considered when performing scheduling in FSM/PSO . Having the idea on each will help to get the clear idea on the logic behind.
- Duration of activity – This parameter to be considered to verify whether the Activity to be scheduled in a shift or during Overtime
- Regions - An activity in a region can only be scheduled to a resource who can work in that region. So checking this for allocate only the appropriate resource.
- Availability – Activity/Place may have restricted times to be performed. These can be defined for a particular activity or a place.

Apart from the captioned concepts bellow parameters are being considered when performing the scheduling.
SLA Periods , Skills ,Parts ,whether the resource is fixed or not , Resource preferences , Shift Time & Utilization , Max Travel to avoid long journeys , Non-working time etc.

Hope this helps.

Thanks,
Tharindu

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

2 replies

Forum|alt.badge.img+9

Hi Sashika,

Mainly there are more concepts considered when performing scheduling in FSM/PSO . Having the idea on each will help to get the clear idea on the logic behind.
- Duration of activity – This parameter to be considered to verify whether the Activity to be scheduled in a shift or during Overtime
- Regions - An activity in a region can only be scheduled to a resource who can work in that region. So checking this for allocate only the appropriate resource.
- Availability – Activity/Place may have restricted times to be performed. These can be defined for a particular activity or a place.

Apart from the captioned concepts bellow parameters are being considered when performing the scheduling.
SLA Periods , Skills ,Parts ,whether the resource is fixed or not , Resource preferences , Shift Time & Utilization , Max Travel to avoid long journeys , Non-working time etc.

Hope this helps.

Thanks,
Tharindu


Sashika Lakshan
Hero (Employee)
Forum|alt.badge.img+7
Tharindu Rasnakawewa wrote:

Hi Sashika,

Mainly there are more concepts considered when performing scheduling in FSM/PSO . Having the idea on each will help to get the clear idea on the logic behind.
- Duration of activity – This parameter to be considered to verify whether the Activity to be scheduled in a shift or during Overtime
- Regions - An activity in a region can only be scheduled to a resource who can work in that region. So checking this for allocate only the appropriate resource.
- Availability – Activity/Place may have restricted times to be performed. These can be defined for a particular activity or a place.

Apart from the captioned concepts bellow parameters are being considered when performing the scheduling.
SLA Periods , Skills ,Parts ,whether the resource is fixed or not , Resource preferences , Shift Time & Utilization , Max Travel to avoid long journeys , Non-working time etc.

Hope this helps.

Thanks,
Tharindu

 

Hi Tharindu, 

Many thanks for the detailed update. This is really helpful.

 