Does anyone know if it is possible to record future time against a project i.e. If it was Tuesday to log Wednesday’s time?

3 replies

Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18
  • Superhero (Partner)
  • 270 replies
  • March 9, 2020

Hi Kate,

 

Yes. You can do project time reporting for  future periods using the Time Registration Window .

 

It will update the time card day and the project transactions accordingly with proper configuration.

 

 

Best Regards,

Shehan Almeida.


Forum|alt.badge.img+3
  • Author
  • 2 replies
  • March 9, 2020

Hi Shenan,

Is there a way to prevent people reporting to future periods without the use of a custom event?

Thanks


Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18
  • Superhero (Partner)
  • 270 replies
  • March 9, 2020

Hi Kate,

 

I am afraid to say that I am not aware of any method of blocking this in a user friendly manner.

 

You can update the Valid to date of the given ‘Report Codes’ to current date every day.  Then employee cant report time for future periods. However, as I said it will not be a very practical solution. 

 