Hi, There is a requirement from the customer that the “Wanted Delivery Date” should not get changed in the Inter-Site order, they need to transfer the original “Wanted Delivery date” created from the demand to the connected PO and CO in the Inter-Site flow without any configuration/customization.

As they have the “Availability Check” selected in the Inventory Part, based on the lead “Wanted Delivery Date” gets changed  in the connected PO based on the “Planned Receipt Date”, and from PO to CO.

And need to know how and where the “Wanted Delivery Date” is used?

Any solutions/suggestions please?

 

 

Hi ​@ProVignSu 

This functionality has been developed in IFS Cloud 23R2 version for the Internal Purchase Direct Flow

It has been controlled through the site parameter “Transfer ATP Info in Internal Direct Deliveries” which is available in Site/Sales and Procurement Tab.

Solution Summary

The system now allows the "Wanted Delivery Date/Time" from the external customer order line to be transferred to the internal purchase order line and internal customer order line.

The feature is specifically for "Int Purch Dir" (Internal Purchase Direct) scenarios and supports multisite operations.

The "Wanted Delivery Date/Time" can only be changed in the external customer order line, not in the internal purchase order line, internal customer order line, or POCO (Purchase Order Customer Order)- when the above parameter is set to true.

The planned delivery date/time is calculated based on the wanted delivery date/time, availability check, and route.

 