Hello,
How does MRP consider safety lead time? I have input a safety lead time and am using planning method A for a top level manufactured part. When I create a customer order for this part, I do not see the safety lead time being considered in the start date, finish date, or need date of the shop order. I also do not see the safety lead time be considered for any shop order requisitions for any of the component parts. See detailed example below:
Part A - safety lead time is 5, part planning method A
Customer Order created for 800 pieces with wanted delivery date of 01/10/2024, and picking lead time of 1 and external transport lead time of 2, so planned due date is 01/07/2024.
Shop Order Requisition is generated for this top-level part with need date of 01/07/2024 and start and finish dates of 01/06/2024. Why doesn’t the shop order requisition have a start and finish dates of 01/02/2024?
Shop Order Requisition is generated for a component part with need date of 01/06/2024 and start and finish dates of 01/05/2024.