Test Plan
- Created and released 2 Material Requisition lines for 2 different Purchase Parts on the same MR.
- RMB on each of the above lines show that 2 Purchase Requisitions created respectively. No Project connection]
- Both the PRs processed and converted to the Pos. Out of the two, only one PO is received and closed. After issuing the materials of the relevant line of that PO, the MR header is in ‘Partially Delivered’ state
- Now the user cancels the other PO and selects ‘No’ to the question to reopen PR lines. So the PR remains in the closed state
- Now how shall I close the MR?
The user actually changed the Due Qty to zero on the MR line and tried to remove the line. But it gives the following message.
“The Material Requisition Line Demand “1” is used by 1 rows in another object (Material Requisition Purchase Order)
IFS App9 UPD14
IFS Support Case ID CS0109018