Hi Team,

Is it possible to set up a Scheduled Job on the “Create Count Report” based on the Work Calendar/Holiday Calendar?

The Customer wants the Schedule to run everyday Monday - Friday, but exclude the Holiday Calendars as there is no reason to create a Count Report for a day that no one will be working.

Thank you,

Alex

Hi ​@Alex_Mee,

This requirement can not be fulfilled using the standard available solutions. 

Though a custom event can be configured to check whether the Count Report created date is a holiday in the site distribution calendar, and if so, the system should cancel the Count Report using a background job.

 

Regards

Abdul Rehman