Would it be possible please to extend the functionality in Planning Workspace > Resource Planner for Unavailabilities to allow editing as well as removing them?

We are currently using PSO version 6.7.


This topic has been closed for comments

3 replies

Userlevel 6
Badge +21

Hi,

I have added this in the Community Idea forum so that it will be considered as an enhancement request.

Userlevel 3
Badge +8

Hi,

You can remove Unavailability via Resource Planner, but cant add or Edit.

 

 

Userlevel 3
Badge +8

Hi,

 

Sorry, you can add as well as delete the Non Availability Via resource planner.

 