Question

Link between work order to several WBS project

  • April 24, 2024
  • 5 replies
  • 67 views

Forum|alt.badge.img+1

Is these anyone to create a link between work order to several WBS project ?

or link between work order task to several WBS project ?

5 replies

Alexander Heinze
Ultimate Hero (Employee)
Forum|alt.badge.img+23

The work order is linked to a single sub project and activity. Tasks are indirectly linked through the work order. 1:n wouldn’t work since you want to allocate work order progress and cost to one project activity.


Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • April 24, 2024

Thank Alexander,

I complete my question, I have a specifique issue and I would like to do a link from 1 work order to several WBS project.

I think it is very complexe and may be, someone do this link

Regards


Mayura Wasantha
Superhero (Employee)
Forum|alt.badge.img+19

Hi @Andrianne - May we know the business need or the use case here? 


HGR
Do Gooder (Employee)
Forum|alt.badge.img
  • Do Gooder (Employee)
  • April 30, 2024

Hi @Andrianne,

What is your use case? Do you need to connect each Work Task on the Work Order to different projects or do you need to have each Work Task connected to several projects?  

 

Regards
Håkan Greko


Forum|alt.badge.img+5
  • Do Gooder (Partner)
  • November 27, 2025

I do have a use case where a customer wants to have 2 projects but they only want one work order but they want multiple tasks on the same work order which would be for each project.  Work order 1 would have 2 tasks one for each project.  Is this possible in newer versions?