Have any other users of the system been able to find a work around with Gantt dependencies when using the scheduler? Our PMs are getting frustrated because they spend time linking dependencies together and then the only way the schedule button on the Gantt view aligns and considers those dates is to just push everything back to the earliest start date of the entire project. It’s not workable for them, just wondering if any other customers have a smart work around.