DOP calendar

  • April 14, 2025
  • 1 reply
  • 35 views

Forum|alt.badge.img+1
  • Do Gooder (Customer)
  • 2 replies

We’re having an issue where the Shop Order and DOP-order time schedule won't align and I’m suspecting that the DOP-order is connect to the calendar defined in the project, rather than the Work Centers defined on each operation in the DOP-order. Could someone please confirm this and if it’s possible to manually connect a DOP-order to a different calendar than the one chosen in the project?

1 reply

Forum|alt.badge.img+3
  • Do Gooder (Employee)
  • 6 replies
  • May 7, 2025

Hi ​@Branke,

The calendar you have defined on the project does not have any impact on the issue you are experiencing. The time misalignment is most likely a result of different calendars being defined on the work centers compared to the manufacturing calendar defined on the site. The DOP order was planned considering the site manufacturing calendar, while the shop order was planned by scheduling its operations based on the calendars assigned to the work centers of the operations. 

In the 25R1 release, we have introduced support for scheduling the operations on a DOP order in the same way as operations are scheduled on a shop order, based on the calendars assigned to the work centers of the operations. To get this behavior, you should enable the new Schedule and Create Load for DOP Order Operations setting on the site. Once the setting is enabled, time misalignments will be prevented. Additionally, a component DOP order that is connected to an operation on the parent DOP order will be planned to to align with the schedule start of that operation, instead of the start of the parent DOP order, which is likely earlier than necessary.

Best regards,
Ellen 