Skip to main content
Question

Can we Complete release update process without Release Update deployment in production environment.

  • January 27, 2025
  • 0 replies
  • 25 views

Forum|alt.badge.img+1

Hello,

We are in the process of upgrading to 24R2 from 23R1 and have completed the Release Update deployment in all environments up to UAT, except for Production. However, during the UAT  testing phase, an issue was highlighted which is ,mentioned in below Topic:

Currently, IFS is investigating this issue, which is preventing us from proceeding with the Release Update deployment in the Production environment. However, as we are running out of time and it is impacting the go-live of our client's business , we would like to proceed with the final step complete Release update process ,i.e. last step in which we do cutover process of complete release update step in Release Update Studio.
So is it okay if we do this step without doing release update deployment in production ? ,

The goal is to retain the Build Place with the new release so that it is available for customizations after the upgrade.

Once the Build Place is upgraded, we plan to deploy our customizations on top of 24R2 in the Production environment at a later stage (currently in the 23R1 state).

Please advise if this approach is feasible.

 

 

0 replies

Be the first to reply!

Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings