After project transactions are created, can we update the internal price without manually editing the project transactions? I need to update the standard cost of employees at the end of the month.

1 reply

Buddhika Kurera
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • 388 replies
  • November 20, 2024

@RASFE Unfortunately, it is not possible. You need to manually edit the transactions. The transactions wont be updated/ synchronized automatically when the standard cost is updated in the application. The transaction gets the values when it is created.

Hope this helps !