FSM--Resource monitoring gantt date issue

  • September 25, 2023
  • 0 replies
  • 15 views

Forum|alt.badge.img+11

FSM-I created a task & assigned to FSE from start date 26 Sep. He started the task on 25 Sep & now allocated start date visible on resource monitoring is 25 Sep. When I allocated the task, I used adjust to schedule feature that applied a calendar on resource & considered 12 hrs per day, so end date was 20 Oct but when he started the task, end date visible on res monitoring screen is 7 Oct which does not give correct picture as the person will work on it till 19/20 oct.

 

 