Hi All,
I have enabled posting control for mandatory pre-posting in PR line which is M100 connected with Project
Then I observed that I’m able to release the PRs without a mandatory pop-up when I’m using Part Requisition lines ( This works for No part Requisition lines ).
1. Why mandatory pre-posting is not working at Part Requestion lines?
2. Is this because M1 always takes values from posting control rather than pre-posting?
Thank you,
Vindya.