How to set up a "4 weeks on and 4 weeks off" calendar?

  • December 30, 2022
  • 2 replies
  • 156 views

Forum|alt.badge.img+4
  • Sidekick (Employee)
  • 10 replies

I have created a Schedule for a Period length = 56 days with the following pattern:

4 weeks (28 days)  with Day Type: 24 hours work in 2 shifts
and 
4 weeks with Day Type:  Non-working days (0 hour).

When I generate a calendar, it is just containing the working hours.

Non-working hours are not generated for the 5th to 8th weeks.

Pictures are attached.

2 replies

MaaretEklund
Do Gooder (Employee)
Forum|alt.badge.img+4
  • Do Gooder (Employee)
  • 12 replies
  • January 4, 2023

Your pictures can not be loaded, could you please re-attach them?


Forum|alt.badge.img+4
  • Author
  • Sidekick (Employee)
  • 10 replies
  • January 4, 2023

Sure, done :)