Any suggestions for entering a single purchase order line and allocating the cost of the line to multiple departments (this is a code part).  Currently consumables are shared among different departments, and they would not like to have to enter multiple lines to spread out the expense.  

Thank you so much for any suggestions

 

Best answer by Adam Bereda

Is department added to a PO line by preposting?

In such a case, yoou can set M116 (or M117 if no part orders are used) posting type for this code part and distribute PO line cost by percentage.  

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

2 replies

Forum|alt.badge.img+16
  • Hero (Customer)
  • 675 replies
  • Answer
  • March 21, 2022

Is department added to a PO line by preposting?

In such a case, yoou can set M116 (or M117 if no part orders are used) posting type for this code part and distribute PO line cost by percentage.  


Forum|alt.badge.img+6
  • Author
  • Sidekick (Partner)
  • 13 replies
  • March 21, 2022

Thank you so much for your response.  I appreciate your time and knowledge