I’ve got the following scenario:
I created a first version of a BOM in EPDM and imported this via Cadlink in IFS. Result Engineering parts (and structure) are created.
I selected the parent part of the BOM to a project deliverable and selected the option copy PDM structure all levels. Result the components of the structure are created as Project Deliverable components. So far so good.
Than the BOM in EPDM is updated (new revisions of components or new components added), via Calink the changes are added to IFS and added to the engineering “structure”.
Now i want to update my project deliverable to with the changes made to the parent part and underlaying parts, but with the option Copy PDM structure all levels , the full list of components is added again so of lot of components are double in the project structure.
Any ideas?
Kind regards,
Vincent Heijmer