Trying to Cancel Project Supply Request on lines no longer required. Getting error message.

  • April 14, 2026
  • 4 replies
  • 22 views

DEBBIEHA
Do Gooder (Customer)
Forum|alt.badge.img+2

Trying to Cancel Project Supply Request on lines no longer required.

Getting the following error message:

The requested operation is not allowed before the Request Line has been cancelled.

The requisition lines are not authorised.

How do I revoke these item lines? 

Many thanks 

 

4 replies

PRODQ
Superhero (Customer)
Forum|alt.badge.img+18
  • Superhero (Customer)
  • April 14, 2026

What’s the Status of the Supply Request?  Has it been converted into a Requisition or RFQ?

 

Linda


DEBBIEHA
Do Gooder (Customer)
Forum|alt.badge.img+2
  • Author
  • Do Gooder (Customer)
  • April 15, 2026

Hi Linda

The lines are sitting on a Purchase Requisition but have not been authorised. 

Debbie 


PRODQ
Superhero (Customer)
Forum|alt.badge.img+18
  • Superhero (Customer)
  • April 15, 2026

What’s the Status of the Pur Req line/s?  Planned?  Released?  Request Created? 

 

Feels like an RFQ has been created off the Purchase Requisition?  “Request” messages on anything Requisition to me make me think Request for Quotation...


DEBBIEHA
Do Gooder (Customer)
Forum|alt.badge.img+2
  • Author
  • Do Gooder (Customer)
  • April 15, 2026

Hi Linda 

Please see attached screenshot of the Status, this is for all the requisition lines not pushed through to a purchase order.

I have checked and there are no Request for Quotations raised against this project.

Many thanks

Debbie