I have a question about project management in IFS, the client I have uses the Tasks tabs for estimates in 7.5.

While migrating to cloud I was wondering what is the difference between using tasks and estimates, is it linked to the activity planned cost source ?

 

Best regards

Hi ​@Abdessamad,

Tasks are for managing timelines and resource assignments, while Estimates are for budgeting and cost forecasting. And yes, estimates are tied to the Activity Planned Cost Source.