Hi,
I have an issue with scheduling projects in Gantt.
My project calendar is 7:00-15:30 / 5 days a week.
When I schedule one single project with lag hours project activities and lag hours in between are scheduled according calendar given on project.
If I schedule 2 projects (multicompany) with the same calendar assigned suddenly lag hours are scheduled according 24/7 calendar instead of project calendar.
If I have 34 lag hours in practice it means:
- When schedule singe project it gives 4 working days (34 hours / 8,5 hour a day)
- When schedule more than one project it gives 1,4 day (34 hours / 24 hours per day)
Is there any way that system follows calendar given on project even if I schedule more than one project in Gantt?
Best regards,
Bernadeta