Question

Schedule multiple projects in Gantt - calendar issue

  • 21 September 2023
  • 0 replies
  • 25 views

Userlevel 3
Badge +5

Hi,

I have an issue with scheduling projects in Gantt.

My project calendar is 7:00-15:30 / 5 days a week.

When I schedule one single project with lag hours project activities and lag hours in between are scheduled according calendar given on project.

If I schedule 2 projects (multicompany) with the same calendar assigned suddenly lag hours are scheduled according 24/7 calendar instead of project calendar.

If I have 34 lag hours in practice it means:

  • When schedule singe project it gives 4 working days (34 hours / 8,5 hour a day)
  • When schedule more than one project it gives 1,4 day (34 hours / 24 hours per day)

Is there any way that system follows calendar given on project even if I schedule more than one project in Gantt?

Best regards,

Bernadeta


0 replies

Be the first to reply!

Reply