Hi Community, 

I have a question regarding project deliverables and the supply option = PMRP. 
I did a test with a purchase part : By defaut the systems sets a supply option = Purchase and i can manually change the value to PRMP. 
Once that done, i went throught the all process
- Approuve the item
- Run GRC
- on the Material plan tab,  RMB to perform PMRP for the part.

The PMRP ran and created a purchase requisition. 
All those information are not visible on “material supply tab”. 
I quite stuck to reserve my part (i did all the flow purchase req/PO/register arrival)

Do you think it’s a normal behavior ? How can I reserve my part ? 

Thanks, 

 

5 replies

Forum|alt.badge.img+9
  • Hero (Employee)
  • 75 replies
  • December 22, 2023

Hi,

 

It can be hard to find, but it is in for example the shipment you want to ship the material with:
 

 

In essence you always need a shipment or a work task or a parent PD Item to reserve the material against

hope this helps a bit

Regards Erik


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Partner)
  • 8 replies
  • January 3, 2024

Hi Erik, 

Thanks for your reply. 
In the shipment view, I can see the button “manual reservation available” when the planning item =shipment is created. 
I saw that there are some possibilities in the material plan to reserve the part. 
I tested the “reserve to shipment” but I did not succed. (it seems available only for shop orders ?)

Here are the steps followed :
1/ Add manufactured part + copy structure
2/ Change supply option to be PRMP + approve the part
3/ Calculate GRC
4/ Modify the option reserve at receipt to be “Reserve to shipment”
5/ Create planning item =shipement
6/ Launch PRMP and shop order process until the receipt of the part. 
After this step, the part is my project inventory but not reserved. 

Is it the right process ? 


 


Marcel.Ausan
Ultimate Hero (Partner)
Forum|alt.badge.img+22
  • Ultimate Hero (Partner)
  • 1142 replies
  • January 3, 2024

@mmoulie I’m not very familiar with Project Deliverables, but in normal Project Demand, there is a flag to reserve the material on receipt.

Maybe there is something like that for Project Deliverables as well?

 


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Partner)
  • 8 replies
  • January 17, 2024

Hi @Marcel.Ausan , 

It seems that if the part is supplied with PRMP/MRP option the only way to reserve the part is to do what @EriLNL explained. 

There is an option quite similar to the one you mentionned “reserve at receive”. But as far as I understand in the IFS documentation there are saying that “The Reserve at Reciept setting is available on shop order plans and purchase order plans”. 

@EriLNL : could you confirm ?

Does someone has any documentation about project deliverables ? 

Thanks for your help, 


Forum|alt.badge.img+9
  • Hero (Employee)
  • 75 replies
  • January 19, 2024

Hi,

it is available in the Material Plans

It has these 3 options:

I think it also reserves against the parent item if the parent does not have a SO or PO yet

Regards Erik