Project Deliverables - Is it possible to get lead time from cum lead time?

  • 27 May 2024
  • 3 replies
  • 36 views

Dear IFS Community,

I have calculated the cumulative lead time for all the parts. When I generate a plan for a manufacturing part in the project deliverables module, it calculates according to manufacturing lead time. Is there a way to make it generate according to cum lead time instead?

 

For instance, 

 

Any help?


Hi @akin ,

The standard application design is to take the manufacturing lead time only. I was hoping that you could look in to a modification to get the cum lead time as required. 

Hope this Helps.
Regards,
Dinudu Kankanamge.
IFS Unified Support