Dear Community,
We use IFS Apps10 UPD21, and we have a lot of projects in the Project module. However we are not fully use all possible capabilities of that module.
One question popped up regarding project capacity planning / forecasting and competencies.
Is it possible to link somehow the project activities and/or tasks to a specific competency?
Main goal would be: With the IFS capacity planning we can foresee the capacity issues, but how can we narrow down the capacity bottlenecks in competency? Like: we would like to foresee, if case of e.g.: welding competency will be a bottleneck in the next January based on the current projects and it’s timelines?
I saw probably - if we would have the Work/Service Order module - we can link a Work Order (with required competency) to an Activity, however maybe that is a bit complicated process for us.
Do you have recommendation for business process and functionality?
Thank you very much in advance for all your input!
Kind regards,
Balazs