Community,
Wondering any tricks for PMRP. We are on APP10 Upd 9.
I created a simple project with only one activity (its finish date is far away in Dec this year), then in this activity demand tab, i entered the Misc Demand a manufactured part. then i run the PMRP, I wish PMRP could like what we do in MRP, drill down to the bottom and have all the demand created with supply, but it only generated the current level, the top part shop order requisition, then nothing at all.
the BOM is a simple BOM, just 2 levels, this part is a multi-site part, top part is manufactured in one site, and the kid is manufactured in another site, both sites are included in the site list of the project.
anything I missed? why PMRP is not drilling down? thank you.