Skip to main content

Hi,

I have got question regarding to functionality Project Resource Forecast. Navigator Path: Project Management\Resources\Project Resource Forecast.

Does anybody know, why it is possible to create more than one row for a same Resource ID x Activity Sequence, in the frm Project Resource Forecast?

I am able to create two exactly the same lines, and I do not even know (after saving), which one was created earlier and which one afterwards. What happens next - if I RMB/Status/Approve the forecast and RMB/Transfer forecast to resource planning - ONLY the last row that was created is transferred to Project/Activity/Resource.

This is probably the standard behavior of the system, but I haven't figured out if this is allowed for any reason, or this should be classified as a bug?

Thank you for your answer in advice, David