I want to define a huge project in project form(the number of activities is a lot). I assign a calendar to project but I need to assign different calendar to some activities of this project(different from what we set up at the beginning). I want to know is it possible to do this? If the answer is YES, that would be great to let us know how we can set this feature?
Product Version: UPD24
Business Impact:

About business impact I should mention that by assigning different calendars to different activities in MSP our % planning progress will be different from what we define in IFS application and we will face wrong data for our monthly progress report to our managers which these reports are queries from IFS data.

Thank You

Adina

Hi Adina, 

Standard IFS application behavior is to set the calendar in the project level. The whole project timeline and the material requirements are planned considering the calendar which is set on the project level. I think you may need to look into a modification/customization to achieve the functionality that you are expecting. 

Reagrds,
Dinudu Kankanamge
IFS unified support. 