Hello,
We are running into an issue with planned/committed costs for material showing an incorrect value when a specific inventory part is added to a project-connected work order. The planned cost is calculated and showing correctly on the work order, but the project connection and activity cost is significantly higher. We have been unable to figure out how this value is being calculated differently compared to the work order. For reference, we are running IFS Apps 10 Update 13.
The part in question is a manufactured part. Below is a screenshot of the inventory part and the cost tab. It shows the current unit cost of one of these parts as $37,745.88.
When I add this part to a work order on the materials tab, it pulls in the correct Planned Cost for that part. It also shows the correct planned cost on the work order Budget tab.
However when we look at the project activity that this work order is connected to, for some reason it is showing a planned/committed cost of $149,060,400.52. This is the only work order connected to this activity and the only part on that work order. If I delete the part from the work order, the materials cost on the activity would show $0, so we know something with this specific part is driving a huge erroneous planned cost. The project connections screen also shows the planned cost is coming from the connected work order and not from something else.
Does anyone know what is causing the project activity planned cost to be significantly different from the actual inventory part and work order planned cost? What is driving the activity planned cost to calculate this?
Thanks,
Evan Edwards