IFS Project module - how to report hours for a resource defined as tool

  • January 29, 2026
  • 3 replies
  • 28 views

Forum|alt.badge.img+2

In IFS resource planning I have defined a resource group as type Tool/Equipment group plus a connected resource representing a machine. I have defined that the equipment should be possible to use both in Maintenance and Project.

I can report hours used on a work order but I cant find where/how I can report consumed hours for the same machine related to a project activity.

My conclusion at the moment is the resources defined as Tools cant not be used in Project module to report hours – is that true?

3 replies

Yathartha Karunananda
Hero (Employee)
Forum|alt.badge.img+11

Hi ​@perx19,

You are correct.  Project Resources are labor resources. 

 


Forum|alt.badge.img+2
  • Author
  • Do Gooder (Partner)
  • January 29, 2026

Ok thanks, so - any future plans for tools also being available in Project module?

Per

 


Yathartha Karunananda
Hero (Employee)
Forum|alt.badge.img+11

Hi ​@perx19,

Not quite sure about that!