when scheduling a project, dependencies are created between activities. The most common type of dependency is finished to start, which means that the activity cannot start until the predecessor activity is finished.
![](https://uploads-eu-west-1.insided.com/ifs-en/attachment/d954a822-9a9e-40c4-a3f9-da0f2a771c6a.png)
When scheduling the project, the system considers these dependencies to plan the start and finish dates of the activities.
Notice that start date had not change after activity 3
![](https://uploads-eu-west-1.insided.com/ifs-en/attachment/781415fa-16d3-4406-ad00-e8ef987e5cb0.png)
May I kindly know if this is due to a basic data issue.
Thank you
Udanee