The quires relating to EV and Cost Progress.
1)How is EV and Cost Progress calculate when Progress Method=Connected Objects?
As we know EV=Planned Cost*Cost Progress.
When Progress Method=Tasks the system works as expected.
But when Progress Method=Connected Objects,
as we change planned cost,
the EV shows no impact but cost progress changed.
Why cost progress change?
2)How is EV and Cost Progress calculate when Progress Method=Connected Objects?
3)Where should we set Top-Down/Bottom-Up Progress Methods on IFS?