Skip to main content
Question

Engineering Change Order Cost


Forum|alt.badge.img+16

Community,

 

We have a problem on the project cost that engineering change order connected to. 

 

in below attached screenshot, you can see in “Change Order Actions”, I have action 20 & 40 connect with cost element H02 100hours, H03 20 Hours. in “Project Hours ECO Connected”, we can see the H02, H03 they are captured from the ECO object. but in “Project Cost _ECO Connected”, you cannot see the exact cost that H02(100hrs) and H03 (20hrs) incur.  you can see cost element H01(10hrs) is also project hours, but it does come with cost $4500, because this cost element is connected to resource ID, and the resource ID is connected with cost element and cost/hr.

I am wondering how to make the hours to be linked to unit cost per hour if connect the ECO hours to project activity?

 

Thank you.

Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings