Could you please let me know if the steps described below are capturing expected behaviour? please notice column comments.

I was expecting the planned cost to get updated after the changed in the PURQ (Purchase Requisition) price but the Planned Cost has not changed (row 5 in table)

ID

Action

Prj Materials & Services window (value)

Prj Monitoring window

 

Comment

 

1

 

Add demand line (MISC. PARTS)

 

 

10,000

 

Planned Cost = 10,000

 

 

 

2

 

Create Project Supply Request

 

10,000

 

Planned Committed Cost = 10,000

 

 

3

 

Create PURQ

 

10,000

 

Planned Cost = 10,000

Planned Committed Cost = 10,000

 

 

4

 

Update Price Manually in PURQ (Change Price/Curr from 10 to 20)

 

10,000

 

Planned Cost = 10,000

Planned Committed Cost = 20,000

 

At the time of creating the PURQ the price of the provider of the external services has changed, hence the manual update on the PURQ

 

5

 

Update Planned Cost & Hours in the demand line

 

10,000

 

Planned Cost = 10,000

Planned Committed Cost = 20,000

 

There is no changes in the Planned Cost. The original value remains despite the Update action

 

Many thanks for your advice

Miguel

Morning,

I should have mentioned I am referring to the Projects module in IFS 24R2.

Thanks

Miguel