Hi,
How to close the Project with open Customer Invoices. These payments are not expected to come or if it comes then Project can be reopen. As of now, requirement is to close the project. Any idea, how it can be done.
Hi,
How to close the Project with open Customer Invoices. These payments are not expected to come or if it comes then Project can be reopen. As of now, requirement is to close the project. Any idea, how it can be done.
Therefore in your scenario, unfortunately it is not possible to Complete the project when there is are unpaid invoices. You need to modify the business process to align with the system design.
Hope this helps !
Therefore in your scenario, unfortunately it is not possible to Complete the project when there is are unpaid invoices. You need to modify the business process to align with the system design.
Hope this helps !
I did think you could re-open a project?
Linda
We do have this option and it does re-open the project (23R1.10)
Hi,
Thanks for your replies. This is a real scenario where we want to close the project (even Financial closure) as we are not expecting the Customer payment against the invoice raised. There must be some solution to this scenario.
Could you write off the debt/cancel the invoice,
Need to check this solution with Finance Consultant.