I would like to report machine time through machine clocking in Shop Floor Workbench (SFWB), but report labor time based on received quantity (if this is possible).  I have set the work center Time Reporting Settings as follows:

where Auto Report Labor Time with Qty is set to Always.  When I test this, I start production on the Shop Order through SFWB and select Machine Time only.  I then go to Approve the operation and receive the reserved Lot Batch with Auto Report of Operations selected.

However, when I review the Labor and Operation history, there is no labor reported.  I was assuming that having Auto Report Labor Time with Qty would result in labor reported (transaction code LABOR_RPT) per the standard based on the received quantity.  However, all that is reported is the OPFEED transaction with qty and machine time.  Is what I am expecting mistaken, or is there a setting that I have missed?

This setting only controls the behavior when a quantity on the operation is auto reported. If your example the quantity was not auto reported but reported when you approved the operation.

If you instead of approving the operation directly would receive it with Auto Report Operations selected, the operation quantity would be auto reported and this parameter would apply.

 