In Apps10 IEE, I want to use the visualizer in the Labor Load Details screen, specifically the Labor Load Summary graphic, to view the scheduled operation hours in a work center for a given day against that work center’s capacity hours. What I get instead for capacity is the sum of labor capacity for the entire labor class. Take for example the below:

The work center ELRPR has 9.32 hours loaded on the date 12/10/24. The work center capacity on any given day is 9.56 hours.Therefore I expect the visual to show that the work center is near fully loaded for that day. Instead, the capacity that is considered in the visual is 434 hours (for every work center), which comes from the labor class’s total capacity for any given day. This causes the visual to show that every work center is near 0% loaded for any given day.

 

 

 

 

The visual therefore is not helpful for viewing work center loads. What do you use to view work center loads?

Hi ​@acjedynak,

Did you try using Machine Load per Work Center? It shows the workload of a certain work center or department on a specific day. Workload is summarized per day and work center.


Hi ​@Yathartha Karunananda,

 

Thank you for the suggestion - I think this will work for us, but only because all of our machine times are set to the same as labor time on routings. If labor time and machine time are different, it would not be effective for viewing labor loads.