In our legacy system, when sales order is created, one job order is automatically created with parent item same as sales item being manufactured part (level 0 item) and as per defined bill of materials.( Level 1,2&3). Level 1 items are sub components. level 2 & 3 are raw materials. Level 1 items assembled to get the level 0 item manufactured completely. Within same job order, there will be multiple level 1 items will be manufactured.

When level 1 items manufacturing completed, we don't have concept of store credit like in ifs application. That means these level 1 manufactured items still remain in the WIP but in reality the item is moved to next level production process for assembling in the same job order.

All the level 1 items remain in WIP until the production process is completed for level 0 item.

Currently we have lot of level 0 & level 1 items still under WIP stage.

we plan to create one shop order for each level 0 & 1 item under WIP but not sure how wip cost from legacy system will be captured in ifs application.

May i know what is the best strategy for migration of WIP (related to production process) into IFS 10 application.