Hi,
we are currently investigating to start using constraint based planning for employees/persons. However, we are struggling.
- How can we assign persons to operations? Can be with APB, or not, we don’t know either way. Does this option give us the possibility to generate planning on a person level?
- How can we also set the labor capacity as a seperate contstraint factor? Currently, APB only takes workcenters into account so we manually check afterwards.
- Is it possible to assign some kind of efficiency to a operator? Lets say person A can do a certain job at 100% (which equals 4 hours). However, if we assign person B to that same operation because A is not available, he will not score 100%. We estimate it to be 50% because he is less well trained, so the operation will take 8 hours. Is something like this possible?
Using IFS Apps 10.
Thanks!