Hi @m.arif ,
Please check attached PDF and let me know.
Thanks,
Jagath
Thanks @Jagath Dharmakeethi , is there a similar document for understanding the costing for Manufacturing part , how does the cost get rolled up from its components and what is the dependency of cost on routing and Workcenters.
Hi Again @m.arif ,
For your Supply site or Site A with part X you need to calculate Cost for Cost Set 2 or any and copy the valid cost set on Cost Set 1.
Then that value will be available in Inventory part Cost tab.
Referring that value, you need to define “Supplier for Purchase part” (window) Price of Part X in Demand site of Site B along with Demand site Connected Purchase part Cost in “Inventory part” window “Cost” tab.
Then the values will be updated.
Other than that, I don’t see any automatic way to roll cost of Supplier site to Demand Site.
Hope this helps,
Thanks,
Jagath
What about cost elements and buckets ,i dont think we need them as we are not manufacturing the finished goods , it will be like only assembling a PC with components purchased from different places. How can i define different selling prices . What about cost set 6 ?