Hi all, first question for the community...What are your best practices for scheduling outside service operations?
In the middle of a routing we send a part to an outside vendor. We currently use machine run factor for example 40 hours to schedule the shop order to be outside for one week. Is there a way to schedule the start and end times for the operation based on the lead time loaded in Supplier For Purchase Part (for the OS part number)?
Additional question, if the confirmed delivery date of the outside service purchase order is later or earlier than the scheduled time, can the scheduled operation reflect that change?
Ty!