Skip to main content
Solved

Required Dates in Estimate Bid Management

  • September 19, 2025
  • 2 replies
  • 67 views

Forum|alt.badge.img+2

Hi,

Does anybody know if the way IFS handles Estimate Item  > Required Date for components of BOM’s has changed from Apps10 to Cloud?

In Apps 10, when I add an Item Type of PRODUCT (Part with BOM) and enter a Required Date, the subcomponent dates are planned.

 

When I perform the same process in Cloud (24R2), my entered Required Date is populated into all sub-components. They are not planned like Apps10.

 

I cannot find any reference to this functionality changing. Does anybody know if and when it was changed?

 

Best answer by Yathartha Karunananda

Hi ​@AntChrisJ,

I checked this in 24R2 and did not notice any difference. It planned the subcomponents, considering the lead times into accounts. Do your parts here have any lead times?

2 replies

Yathartha Karunananda
Hero (Employee)
Forum|alt.badge.img+11

Hi ​@AntChrisJ,

I checked this in 24R2 and did not notice any difference. It planned the subcomponents, considering the lead times into accounts. Do your parts here have any lead times?


Forum|alt.badge.img+2
  • Author
  • Do Gooder (Partner)
  • September 29, 2025

Thankyou for confirming ​@Yathartha Karunananda, I do have leadtimes throughout the BOM, so it may be something else or a bug.