Required Dates in Estimate Bid Management

  • Sep 19, 2025 11:05 AM UTC
  • 2 replies
  • 104 views

Forum|alt.badge.img+2

Hi,

Does anybody know if the way IFS handles Estimate Item  > Required Date for components of BOM’s has changed from Apps10 to Cloud?

In Apps 10, when I add an Item Type of PRODUCT (Part with BOM) and enter a Required Date, the subcomponent dates are planned.

 

When I perform the same process in Cloud (24R2), my entered Required Date is populated into all sub-components. They are not planned like Apps10.

 

I cannot find any reference to this functionality changing. Does anybody know if and when it was changed?

 

Best answer by Yathartha Karunananda

Hi ​@AntChrisJ,

I checked this in 24R2 and did not notice any difference. It planned the subcomponents, considering the lead times into accounts. Do your parts here have any lead times?

View original

2 replies

Yathartha Karunananda
Superhero (Employee)
Forum|alt.badge.img+12

Hi ​@AntChrisJ,

I checked this in 24R2 and did not notice any difference. It planned the subcomponents, considering the lead times into accounts. Do your parts here have any lead times?


Forum|alt.badge.img+2
  • Author
  • Do Gooder (Partner)
  • Sep 29, 2025 6:54 AM UTC

Thankyou for confirming ​@Yathartha Karunananda, I do have leadtimes throughout the BOM, so it may be something else or a bug.