Hello, IFS Heroes…
I have found in IFS official documentation this description:
‘If using the PM Grouping Rule on PM actions, the PM actions with same values for grouping rule parameters defined and that fall due at same time will be generated into one work order. This will result in all work list lines planned on the PM actions becoming work tasks on the generated work order. “
Key words of these statement “fall due at same time will be generated into same work order” I consider this as if works should be done at a same day it will be grouped to one work order. But, unfortunately, all works grouped in one work order from start of a month and to a end of the month.
Is it feature or bug? What do you think?