Good morning community! We have a scenario where we have a sub assembly on our PS. We would like to flatten the PS to move the sub assembly components to direct components of the finished good eliminating the need to transact the sub assembly. This sub assembly that we want to remove from the PS is used in multiple finished goods (it is a blend of materials). We want the ability to see demand for the blend (sub assembly) but not actually schedule it or produce it unless we need to put it in barrels to be store in inventory (lot controlled).
We have tried phantom parts, but they only seem to explode the materials in the shop order as opposed to the operations. We want both to be part of the finished good.
We have tried putting the blend in our PS as a zero QPA, but had to set the component to ‘allow as not consumed’ to get it to work. This created an error because it is lot controlled (which it needs to be).
And we cannot put both the sub assembly and raw components on the shop order because it would skew the cost.
How do others deal with this type of scenario?
Thank you for your help!
Robin