Hi,
it seems not be possible to peg a customer order line with a purchase order line, which originated from a DOP. Is that so, or am I doing something wrong?
Situation:
To finish a DOP, we need to have 3 times component A. We create a DOP, a pegged purchase order is created to order 3x Component A. Related shop orders are also created.
2 times component A are delivered. The last part will be delayed. We decide to finish the DOP and send the end product to the costumer, and when the last component A is received we will sent to customer who is able to built that component in the machine himself.
This is how we do it:
- We adjust the shop order, so we can finish it with 2 components (qty per assembly is now 2 instead of 3).
- We add a line to the costumer order with Component A, so we can sent it afterwards to the client.
- We close the DOP
- We would like to peg the existing purchase order with the customer order line, to make sure that part goes to the customer when it arrives. However, that doesn’t seem possible?