Dear All,

 

related to seasonal business we have the case that some machine capacities are fully loaded. To reach necessary quantity we set up additional manual assembly process for that time. So for one product which needs to be assembled we have an automatically process (e.g. for 80% of produced pars) and additional to that an manual process (e.g. for 20% of produced parts). 

 

If we use the routing for machine process for calculation, the part is calculated to cheap, if we use the manual process the part is calculated to expensive.

 

Is there a kind of possibility to mix that both production processes for one part number for calculation, which not impact production planning and logistic etc.?

 

Thanks in advance for feedback

 

regards 

Sebastian