When scheduling a block of shop order operations in sequence, what logic is used to determine the sequence in which the operations are scheduled? Is the final sequence based on prioritization by Order Need Date, Operation Finish Date, Remaining Resource Hours, something else?
Solved
Operation Block Sequencing Logic
Best answer by Björn Hultgren
Glad you found the operation block functionality!
Originally the logic only used the scheduled start date/time of the operation. I.e. the operations will be scheduled in the same order as they where scheduled before the rescheduling.
With apps 10 update 8 (I think) the new operation sequencing logic was introduced in IFS Aurena. With this logic you can sequence operations without using operation blocks, that logic will sequence based on
- Characteristic Values.
- Operation Priority.
- Original scheduled start date/time
At the same time the logic for scheduling operation blocks was also adjusted to primarily consider the operation priority. So now it looks like:
- Operation Priority.
- Original scheduled start date/time