Question

No available resources found when scheduling order

  • 29 June 2022
  • 1 reply
  • 289 views

Badge +1

Hello,

 

I am getting this error 

But I have checked the Routing, the Workcenter, the resource templates, and resources to make sure that they are setup correctly and they are.  I am thinking that maybe there is a company wide setting that needs to be set.


1 reply

Userlevel 6
Badge +20

Likely one of two things.

  1. The Work Center is set to use the Calendar ‘*’, which I know has caused issues such as this before.
  2. The resource in the Work Center is not valid on 16-JUN-22 due to a setup issue on the validity of the Resource.

When you look at the Resource Detail for the resource(s) in this Work Center, are there any for which the validity period does not include the date 16-JUN-22?

 