Hello,
In 24R2 - MS 1 is always creating the Supply request (Shop Ord Req) considering the product structure revision based on the Due date even though ‘Use Current Revision for Past Due Supplies’ check box is enabled at Site level.
With the Same setup at site level, we tried the below scenario
- Created manual Shop Ord Req with the due date as in the MS generated Shop Ord Req, it is picking up the latest revision, not considering the due date of the shop order.
- Manually updating the quantity in MS 1 generated Shop Ord Req, the Product structure revision changed to the latest revision in the Shop requisition
Conclusion: MS1 is not working as expected with ‘Use Current Revision for Past Due Supplies’ check box is enabled at Site level.
I am not sure whether i need to setup some thing more to Use this feature for MS1.
Appreciate your help in advance.
Thanks,